Argyll Array Project Update #27 – May 2012

Scottish Power Renewables logo

Argyll Array Website

The project website www.argyllarray.com has now been updated to reflect the recent changes to the project timings. It also now carries electronic copies of all the updates published in An Tirisdeach and copies of the indicative photomontages used at the June 2011 Public Information Day.

New project timetable

A number of people have asked for clarification of the new timetable for the project. I’ve therefore listed the most important revised dates below. It should be noted that these dates are those that are currently planned and are subject to change, especially the milestones that are still some years in the future. Some aspects, such as the date of the planning decision are also outwith SPR’s control.

  • · 2012/13?research and preparation for the Environmental Statement
  • · Mid 2014? Environmental Statement issued for pre-application consultation
  • · Late 2014? planning application submitted
  • · 2015/16?planning decision
  • · 2016/17?final investment decision by SPR
  • · 2018?begin construction of electrical transmission infrastructure
  • · Early 2020?begin offshore turbine installation
  • · Late 2020?first electricity production from the wind farm Cable route
  • As I’ve said in previous updates, the electricity generated at the Argyll Array wind farm will connect to the National Grid at Dalmally. Over the last year, SPR have looked at a number of options for where to lay the cable, and have now revised this to two options

    • · one undersea to Mull, then crossing Mull through Loch Na Keal towards Salen, then running south east along the A849 towards Craignure
    • · the other passing undersea by the south of Mull. Both routes would land north of Oban and then follow the A85 to Dalmally.

    underground cable map

    These are the routes marked blue on the map. We won’t know which of these is preferred until we’ve undertaken the geophysical survey for the cable route. (The grey coloured routes are no longer options and the thin red border defines the area of search for the route.)

    All of the onshore cables will be underground, both on the mainland and if they cross Mull. We will undertake environmental and technical surveys of the routes in 2013, and following these will be able to define the exact proposed route of the cable.

    Future updates

    • · What’s in an Environmental Statement?
    • · What’s a pre?application consultation?
    • · Support for education and training in renewable energy in Tiree

    Questions or comments
    If anyone has any questions or comments on any of the above, or indeed any aspect of the project, please contact me at –

    Donnie Campbell, ScottishPower Renewables Community Liaison Officer, Machair, Kilmoluaig in the first instance. My land line telephone number is 220 352, mobile number 07881 983 753 and email donnie@argyllarray.com

Leave a Reply

Your email address will not be published. Required fields are marked *